Project Timeline
- Where is the project now?
-
Spring 2023
The project is in the final phases of construction and is on schedule to open on July 1, 2023, in time for the fall 2023 football season.
-
- Project timeline
-
February 7, 2018 - .
June 5, 2019 - Ceremonial bench removal marks beginning of demolition on east side of CEFCU Stadium.
February 2020 - Spartan Athletics partners with Webcor and HOK to design and build the new Spartan Athletic Center.July 2020 - Removal of the east side hill at CEFCU Stadium.
November 17, 2020 - CSU Board of Trustees votes to approve building plans. Construction begins.
Summer 2023 - Project completion and official opening.
-